PRODUCTION GUIDE

Bill of materials example: building a multi-level BOM step by step

By Windfire Admin · Updated November 17, 2026

A bill of materials (BOM) is the list of everything needed to make one unit of a product: raw materials, purchased parts and sub-assemblies, with the quantity of each. It drives purchasing, production, costing and inventory. This guide builds a real-world style BOM for a steel tool cart, rolls up its cost, and covers the mistakes that cause most BOM problems.

What a BOM contains

At minimum, each line needs:

  • Item number and description
  • Quantity per one unit of the parent
  • Unit of measure (each, meter, kilogram)
  • Make or buy

Useful extras: scrap or yield allowance, reference designators or positions, revision, and notes such as approved alternates. Our bill of materials template includes these columns.

Single-level vs multi-level

A single-level BOM lists only the direct components of one parent. A multi-level BOM shows the whole structure: the product, its sub-assemblies, and their components, each with a level number. Level 0 is the finished product.

Use a sub-assembly level when you build, stock, inspect or sell that sub-assembly separately. If you weld a frame on one day and assemble carts on another, the frame should be its own item with its own BOM.

Example: TC-100 steel tool cart

LevelItemDescriptionQty perUoMMake/BuyUnit costExtended
0TC-100Steel tool cart1eaMake
1FR-200Welded frame1eaMake$33.35$33.35
2ST-2525 mm square steel tube (6.0 m + 5% scrap = 6.3 m)6.3mBuy$4.50$28.35
2PL-03Corner gusset plate4eaBuy$1.25$5.00
1SH-300Shelf, 16-gauge steel2eaBuy$14.00$28.00
1CA-410100 mm caster4eaBuy$6.50$26.00
1HW-500Hardware kit1kitBuy$3.20$3.20

Rolling up the material cost

  1. Frame (level 2 up to level 1): 6.3 m × $4.50 = $28.35, plus 4 × $1.25 = $5.00, so FR-200 material = $33.35.
  2. Cart (level 1 up to level 0): $33.35 + $28.00 + $26.00 + $3.20 = $90.55 material per cart.

Then add labor from the routing. If cutting takes 0.3 hours, welding 0.8 hours and final assembly 0.4 hours, that is 1.5 hours. At an example rate of $38 per hour, labor is $57.00, giving $147.55 before overhead. Try your own numbers in the BOM cost calculator.

Scrap and yield allowances

The frame needs 6.0 m of tube, but cutting loses some to kerf and offcuts. A 5% scrap allowance raises the BOM quantity to 6.0 × 1.05 = 6.3 m. Without it, every job will be short of material and planning will under-buy. Base the percentage on what you actually lose, measured over several jobs, and keep it as a separate field if your system allows so the base quantity stays clear.

Exploding the BOM for a job

For an order of 50 carts, multiply down the levels:

  • FR-200 frames: 50
  • ST-25 tube: 50 × 6.3 = 315 m
  • PL-03 gussets: 50 × 4 = 200
  • SH-300 shelves: 100; CA-410 casters: 200; HW-500 kits: 50

Compare these with stock on hand and on order to see what to buy. That is the basis of requirements planning, explained in our MRP vs ERP guide.

BOM vs routing

The BOM says what goes into the product. The routing (or method) says how it is made: operations, work centers, setup and run times, instructions. Keep them separate. If you add "welding" as a line on the BOM, you cannot schedule it, and if you put the steel tube in the routing, purchasing cannot see it.

Common BOM mistakes

  • Wrong units of measure. Buying tube by the 6 m length and consuming it by the meter needs a clear conversion, or stock will drift.
  • Missing consumables. Welding wire, paint and adhesives are often left off. Either add them with an estimated quantity or treat them as overhead, but decide deliberately.
  • Phantom levels that do not exist on the floor. Sub-assemblies that are never built separately add transactions with no benefit.
  • Uncontrolled changes. Editing a BOM while jobs are open without a revision makes it impossible to know what was actually built.
  • No scrap allowance where material is cut or machined.

Engineering BOM vs manufacturing BOM

An engineering BOM (EBOM) reflects the design: the parts on the drawing, organized the way engineering thinks about the product. A manufacturing BOM (MBOM) reflects how the product is actually built, including sub-assemblies created for the floor, packaging, consumables and scrap allowances. Small shops often keep a single BOM, which works as long as it matches the build. When engineering and production disagree about what a product contains, the manufacturing BOM is the one that should drive purchasing and jobs.

Keeping BOMs accurate

Compare actual material issued to jobs against the BOM quantities. If jobs regularly use 7 m of tube instead of 6.3, either the BOM or the process is wrong. Review the biggest gaps monthly, and give every BOM change a revision and an effective date.

Frequently asked questions

What is a multi-level BOM?

A bill of materials that shows the full product structure: the finished product, its sub-assemblies and their components, each with a level number.

What is the difference between a BOM and a routing?

The BOM lists the materials and components. The routing lists the operations, work centers and times needed to make the product.

How do I add scrap to a BOM?

Multiply the net quantity by one plus the scrap rate. For 6.0 m with 5% scrap, the BOM quantity is 6.3 m.

Should consumables be on the BOM?

Include them if you want them planned and costed per unit; otherwise treat them as overhead. Either way, make it a deliberate choice.