BOM cost roll-up calculator

Add up what one unit really costs to make: components with scrap allowance, labor and overhead, then multiply by the batch.

Free, no sign-up. Published by Windfire Admin · Updated November 17, 2026

Components (one level)
ComponentQty perUnit costScrap %ExtendedRemove
Per-unit labor and overhead

What it means

A cost roll-up adds the cost of every component in a bill of materials (BOM), allowing for the material lost to scrap, then adds the labor and overhead needed to make one unit. The result is the standard cost you quote from and compare actual job costs against.

For a multi-level assembly, roll up each sub-assembly first and enter its cost per unit as one component line in the parent. Outside processing such as plating or powder coating can go in as a component line too.

The formula

Extended cost = quantity per unit × unit cost × (1 + scrap % ÷ 100)

Cost per unit = sum of extended costs + labor per unit + overhead per unit

Batch total = cost per unit × batch quantity

Worked example

A welded frame uses 2.5 m of tube at $4.20/m with 5% scrap, 2 plates at $3.10, 8 fasteners at $0.12 and outside powder coating at $6.50. Labor is 0.75 h at $38/h = $28.50 and overhead is $9.00 per unit.

  • Tube: 2.5 × 4.20 × 1.05 = $11.025
  • Plates: 2 × 3.10 = $6.20
  • Fasteners: 8 × 0.12 = $0.96
  • Powder coat: 1 × 6.50 = $6.50

Material = $24.685; cost per unit = 24.685 + 28.50 + 9.00 = $62.19; a batch of 50 = $3,109.25.

FREQUENTLY ASKED

Questions and answers

What is a BOM cost roll-up?

It is the total cost of one finished unit, built up from the cost of every component in its bill of materials plus the labor and overhead to make it.

How should I handle scrap?

Enter the share of material you expect to lose (offcuts, setup pieces, rejects) as a scrap percentage on that line. The calculator increases the extended cost accordingly.

How do I cost a multi-level assembly?

Work from the bottom up: roll up each sub-assembly on its own, then use its cost per unit as a component line in the next level.

Is my data saved or sent anywhere?

No. The calculation runs in your browser. Use Download CSV to keep a copy.

WHEN A SPREADSHEET STOPS BEING ENOUGH

Compare the estimate with what the job actually cost

WindFire supports simple parts and multi-level assemblies, and job costing shows cost to date and the estimate to finish against each job's original estimate, flagging jobs whose margin falls below your target.

Learn the method

More free tools