Takt time vs cycle time vs lead time: formulas and a worked example
Takt time vs cycle time vs lead time explained with formulas and a worked line-balancing example: find the bottleneck and how many operators you need.
Read the guideFREE PRODUCTION TOOL
Find the pace your line must keep to meet demand, how many stations or operators that takes, and what your current setup can make in a day.
Takt time is the pace of customer demand: the available production time divided by the number of units customers need in that time. If a unit leaves the line every takt period, you meet demand without overproducing.
Cycle time is how long one unit actually takes at a station. When the cycle time is longer than takt, you need parallel stations, more operators or a faster process. The efficiency figure lets you allow for changeovers, small stops and quality checks. A load near or above 100% means the plan has no room for problems.
Available time = (shift length − breaks) × shifts per day
Takt time = available time ÷ customer demand
Stations needed = cycle time ÷ takt time, rounded up
Units per station per day = available time × efficiency ÷ cycle time, rounded down
Two 480-minute shifts with 30 minutes of breaks each, customer demand of 540 units a day, a cycle time of 240 seconds and 85% efficiency.
FREQUENTLY ASKED
Takt time comes from customer demand: how often a unit must be finished. Cycle time comes from the process: how long a unit actually takes. You want cycle time per station at or below takt time.
Yes. Remove planned breaks, meetings and planned maintenance. Leave unplanned stops in the efficiency figure instead.
Use your measured figure if you have one (for example from overall equipment effectiveness). If not, 80 to 90% is a common planning assumption for a running process.
It fits repetitive work best. In a job shop with varied routings, the same arithmetic helps check whether a workstation has enough hours for the week's load.
WHEN A SPREADSHEET STOPS BEING ENOUGH
WindFire's scheduler places released operations within each workstation's working hours and capacity, in step order, and protects work already underway.
Takt time vs cycle time vs lead time explained with formulas and a worked line-balancing example: find the bottleneck and how many operators you need.
Read the guideCapacity planning for small manufacturers: calculate available and rated capacity, compare load by work center, find bottlenecks and fix overloads.
Read the guideRoll up material, scrap, labor and overhead into a cost per unit and per batch. Export to CSV.
Open the toolFind the stock level at which to place the next order, from daily usage, lead time and safety stock.
Open the toolEconomic order quantity: the order size that balances ordering cost against holding cost.
Open the tool