Reorder point formula: when to order, with worked examples
The reorder point formula explained: lead time demand plus safety stock. Worked examples for purchased and made parts, plus common mistakes to avoid.
Read the guideFREE INVENTORY TOOL
Work out the stock level that should trigger your next purchase or production order, so material arrives before the shelf runs empty.
The reorder point is the on-hand quantity at which you place a new order. If you reorder at that level, the stock you have left should cover what you use while you wait for the delivery, with the safety stock left over to absorb a late delivery or a busy week.
Use the same unit everywhere: if usage is per working day, count lead time in working days too. Recalculate when usage or supplier lead times change. A part that is used faster, or a supplier that gets slower, both raise the reorder point.
Reorder point = average daily usage × lead time in days + safety stock
Demand during lead time is the first part (usage × lead time). The safety stock calculator helps you size the buffer.
A shop uses 40 brackets a day. The supplier delivers 7 days after an order. The shop keeps 100 brackets as safety stock.
When the shelf count drops to 380 brackets, place the next order.
FREQUENTLY ASKED
It is the stock level that tells you to place the next order. When on-hand quantity falls to the reorder point, you order, and the remaining stock covers usage until the delivery arrives.
Either works if you are consistent. If usage is measured per working day, express the lead time in working days as well.
Enter zero. The reorder point then equals the demand during lead time, which leaves no buffer for late deliveries or demand spikes.
The reorder point says when to order. The reorder quantity says how much to order; the economic order quantity (EOQ) is one common way to choose it.
WHEN A SPREADSHEET STOPS BEING ENOUGH
In WindFire you find stock across warehouses and storage locations, down to shelves, drawers and bins, and set replenishment defaults for made and purchased items, so purchasing sees what needs buying.
The reorder point formula explained: lead time demand plus safety stock. Worked examples for purchased and made parts, plus common mistakes to avoid.
Read the guideThree common safety stock methods: max-minus-average, demand variability and combined variability.
Open the toolEconomic order quantity: the order size that balances ordering cost against holding cost.
Open the toolTurnover ratio and days of inventory from cost of goods sold and beginning and ending inventory.
Open the tool