PRODUCTION GUIDE
Capacity planning for small manufacturers: a practical method
Capacity planning answers a simple question: can we do the work we have promised, on time, with the people and machines we have? Without it, a shop accepts orders until the floor is jammed, then discovers the problem through late deliveries and overtime. This guide shows a straightforward method using hours by work center, with a worked example.
Step 1: calculate available capacity
Start with the time each work center is scheduled to work:
Available hours = number of machines (or people) × hours per shift × shifts per day × days
Example: a CNC milling cell has 3 machines running 2 shifts of 8 hours, 5 days a week: 3 × 8 × 2 × 5 = 240 hours per week.
Step 2: adjust to rated capacity
No work center produces for every scheduled hour. Two factors bring available hours down to what you can realistically plan for:
- Utilization: the share of scheduled time actually spent working, after breaks, meetings, maintenance and waiting for material or operators.
- Efficiency: how actual output compares with standard times. If jobs typically take longer than their routings say, efficiency is below 100%.
Rated capacity = available hours × utilization × efficiency
If utilization is 85% and efficiency 90%: 240 × 0.85 × 0.90 = 183.6 standard hours per week.
Measure both from your own records: compare clocked time on jobs against scheduled time for utilization, and standard hours earned against actual hours for efficiency. If you track OEE, it gives similar insight for individual machines.
Step 3: calculate the load
Load is the standard hours of work scheduled for each work center in the period. For each job's operation at that work center:
Operation hours = setup time + (quantity × run time per piece)
| Job | Qty | Setup | Run per piece | Hours |
|---|---|---|---|---|
| J-501 | 400 | 3.0 h | 6 min | 3 + 40 = 43.0 |
| J-502 | 120 | 2.5 h | 15 min | 2.5 + 30 = 32.5 |
| J-503 | 1,000 | 4.0 h | 3 min | 4 + 50 = 54.0 |
| J-504 | 60 | 2.0 h | 40 min | 2 + 40 = 42.0 |
| J-505 | 250 | 3.5 h | 7.2 min | 3.5 + 30 = 33.5 |
| Total | 205.0 |
Step 4: compare load with capacity
Load % = load hours / rated capacity × 100
205.0 / 183.6 = 111.7%. The cell is overloaded by 205.0 − 183.6 = 21.4 hours this week. Do this for every work center and the overloaded ones stand out immediately, often weeks before the problem would show up as late jobs. The work center that is overloaded most often is your constraint.
Step 5: resolve the overload
Options, from least to most disruptive:
- Move work in time: pull a job forward into a lighter earlier week, or push one with a later due date back.
- Move work in space: route an operation to an alternate machine that can do it.
- Add hours: overtime or a Saturday shift. Here, 21.4 hours across 3 machines is about 7 hours each.
- Reduce setup hours by grouping jobs with similar setups, then running them back to back.
- Subcontract an operation or a whole job.
- Renegotiate the due date with the customer, early and honestly.
And a step before all of these: when quoting new work, check the load in the weeks it would hit the floor. A delivery date set without looking at capacity is a guess.
Finite vs infinite scheduling
Infinite scheduling places each operation on the date it is needed, ignoring capacity, then shows you the overloads to fix. Finite scheduling only schedules work into available capacity, pushing operations later when a work center is full, so it shows realistic finish dates. Small shops often start with an infinite load report like the one above and move to finite scheduling for their constraint work center.
Protect the bottleneck
Capacity in a shop is set by its constraint. An hour lost at the bottleneck is an hour lost for the whole shop; an hour lost at a work center with spare capacity costs almost nothing. So:
- Keep a small buffer of ready work (material and paperwork ready) in front of it.
- Schedule maintenance and breaks so it keeps running where possible.
- Inspect before the bottleneck, so it does not spend time on parts that are already scrap.
- Release new jobs to the floor at the pace the bottleneck can handle. Releasing more just builds queues and stretches lead time.
Rough-cut capacity for longer horizons
For the next 3–6 months, use a rough-cut plan: average hours per unit for each product family at each key work center, multiplied by the forecast. If a family needs 0.4 hours on the press brake per unit and you forecast 600 units a month, that is 240 press brake hours. Compare with monthly rated capacity to decide on hiring, shifts or equipment early. For line-style production, the takt time and capacity calculator gives the same answer from the demand side.
Frequently asked questions
What is the difference between available and rated capacity?
Available capacity is scheduled hours. Rated capacity adjusts those hours for utilization and efficiency to show what you can realistically plan for.
How do I calculate load?
For each operation at a work center, add the setup time to quantity × run time per piece, then add up all operations planned in the period.
What is finite scheduling?
Scheduling that only places work into available capacity, pushing operations later when a work center is full, so finish dates are realistic.
What should I do when a work center is over 100% loaded?
Move work earlier or later, use alternate machines, add overtime, group similar setups, subcontract, or agree a new date with the customer.