REPLENISHMENT GUIDE
Lead time calculation: supplier, manufacturing and customer lead time
"Lead time" means the time between starting something and finishing it, but in a manufacturing business there are several kinds, and confusing them causes most planning mistakes. This guide explains each kind, shows how to calculate it, and how to measure its average and variability from your own records.
The three lead times that matter
- Supplier (purchasing) lead time: from deciding to buy until the material is in stock and usable.
- Manufacturing lead time: from releasing a job to the floor until the finished part is in stock.
- Customer lead time: from receiving the customer's order until it is delivered.
Supplier lead time
The quote from the supplier is only part of it. The full replenishment lead time includes your own steps:
Replenishment lead time = internal processing + supplier lead time + transit + receiving and inspection
Example: 2 days to raise and approve the purchase order + 10 days for the supplier to ship + 3 days in transit + 1 day to receive, inspect and put away = 16 days.
If your reorder point uses the supplier's quoted 10 days, you will reorder six days too late every time. This is why the reorder point should be based on the full replenishment time.
Measuring supplier lead time from history
For each recent purchase order, measure days from order date to receipt date. Suppose the last six orders took 14, 17, 15, 21, 16 and 13 days.
- Average: (14 + 17 + 15 + 21 + 16 + 13) / 6 = 96 / 6 = 16 days
- Deviations from the average: −2, +1, −1, +5, 0, −3
- Squared: 4, 1, 1, 25, 0, 9; sum = 40
- Sample standard deviation: √(40 / (6 − 1)) = √8 = 2.83 days
The average goes into your reorder point; the standard deviation goes into your safety stock calculation. In a spreadsheet, use AVERAGE and STDEV.S. Use working days or calendar days consistently, matching how you measure usage.
Also look at the outliers. The 21-day order might have been held up by a holiday or a part shortage at the supplier. If it was a one-off with a known cause, you might exclude it; if late deliveries like that happen regularly, keep it in.
Manufacturing lead time
Manufacturing lead time is the sum of five elements for each operation in the routing:
Manufacturing lead time = queue + setup + run + wait + move
- Queue: waiting in front of the machine or work center before work starts.
- Setup: changing over the machine for this job.
- Run: quantity × time per piece.
- Wait: waiting after the operation, for example for parts to cool or for inspection.
- Move: transport to the next operation.
Example: a job of 200 brackets with three operations:
| Operation | Queue | Setup | Run | Wait + move | Total |
|---|---|---|---|---|---|
| Laser cut | 8 h | 0.5 h | 200 × 0.75 min = 2.5 h | 1 h | 12 h |
| Press brake | 16 h | 1 h | 200 × 1.5 min = 5 h | 2 h | 24 h |
| Powder coat | 24 h | 1 h | 4 h (batch) | 3 h | 32 h |
| Total | 48 h | 2.5 h | 11.5 h | 6 h | 68 h |
With one 8-hour shift a day, 68 hours of elapsed shop time is 8.5 working days. Only 14 of those hours (setup + run) are actual work; queue time is 48 hours, about 70% of the total. That is typical of job shops and is the main lever: reducing queues by releasing less work at once and scheduling to capacity shortens lead time more than speeding up machines. See our guide to capacity planning.
Customer lead time
For a make-to-order product, customer lead time is roughly:
Customer lead time = order processing + material lead time (if not in stock) + manufacturing lead time + shipping
Example: 1 day to enter and review the order + 16 days to buy material that is not stocked + 8.5 days in production + 2 days shipping = 27.5 working days. If you stock the material, it drops to 11.5 days. That trade-off, inventory against speed, is a decision worth making deliberately for your fastest-selling products.
Cumulative lead time
For a multi-level product, the cumulative (or critical path) lead time is the longest chain through the bill of materials: the longest-lead purchased part, plus the time to make each sub-assembly above it, plus final assembly. It tells you the shortest time you could build the product from nothing.
Keep lead times current
- Review supplier lead times quarterly from actual receipts, not quotes.
- Update manufacturing lead times when queue times change, for example when the shop gets busier.
- Recalculate reorder points and promise dates when lead times move.
Frequently asked questions
How do you calculate lead time?
Measure the time from start to finish for each event, such as order date to receipt date for purchases, and average the results. Include internal steps like approval and receiving, not just the supplier quote.
What is the difference between lead time and cycle time?
Lead time is total elapsed time, including waiting. Cycle time is usually the time to complete one unit or one operation of actual work.
Why does queue time matter so much?
In many job shops most of the manufacturing lead time is spent waiting in front of work centers. Reducing queues shortens lead time more than speeding up the work itself.
Should lead time be in working days or calendar days?
Either, as long as it matches how you measure usage and plan. Mixing the two causes errors in reorder points and promise dates.